1) The installing of mainframe:

The axes of rod mill main frame should be level, measured on top of big flange of medium-altitude bearing that on two ends, the height should be identical. If has error, it is allowed that feeder is higher the output 1mm. Seen from bearing cover of medium-altitude bearing on two ends, the around gap between medium-altitude bearing and bearing cover should be identical, and the out and the inside bearing cover too.

2) The installing of driving part:

After mainframe is identical, driving part can be installed. First, check quality of driving part, especial check concentric of small gear wheel bearing and reducer low speed bearing; concentric of reducer high speed bearing and motor bearing, if necessary to adjust and tighten. Set the big bear wheel of mainframe as standard, install and adjust driving part. Make the width between small gear wheel and big gear wheel even. Make the side of the small gear wheel and the big gear wheel parallel. The smallest gap is 0.25mm. Seen from track of big and small touched, the touched track takes up 60% from whole length, and 40% from whole height.

If the touched track leans to one side, means the gear side is not parallel. If the driving big gear wheel crowded, means the gap of the gear wheel is too small, adjust it bigger. After installing, verifying proper, and then can start the hollow experimental work. The experimental work is in the charge of skilled the operator and obey the operation procedure strictly.

Because the haydite has absorption ability, in the preparation of concrete, the sum of water is bigger than ordinary concrete, usually used to increase the water absorbing capacity of the ceramsite 15 minutes.For ceramsite which deposited in the open air, the actual water content will have a larger change, the top and bottom of the heap ceramsite is different, morning, noon and night are differ, when the climate changes, especially after the rain, moisture content change of ceram